Kowalsky Construction Update: 1/23-1/27

On Monday, 1/23, both the Annex and the Addition will undergo an air leak test to ensure that buildings' envelopes are sealed tight.
 
Throughout the week, the siding will go on the Addition, and the re-construction of the Annex exterior will continue.  Electrical rough-in will continue in the Addition along with the plumbing and mechanical rough-ins.  The electrical, plumbing, and mechanical rough-ins are nearly complete in the Annex; the crew will finish its weather and sound insulation and schedule sheetrock in the very near future.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).

Kowalsky Construction Update: 12/19/16-1/3/17

While VSC is on the holiday break, the construction crew will be framing the interior of the Kowalsky Annex and putting the new roof system in place, and the Mechanical, Electrical and Sprinkler teams will be roughing in their work (in both the Annex and Addition). 

Beginning 12/19, the crew will be setting the trusses, which are on schedule to be tied into the main house by the 23rd; there will also be siding prep, and window installation on the Addition after the building is dried in. The porch framing should be underway after the turn of the New Year. 

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm). The office will be closed for business from 12/23/16-1/2/17.

Kowalsky Construction Update: 12/12-12/16

Throughout the week, the second floor walls and partitions on the Kowalsky Addition will be completed ahead of setting the roof trusses on Friday, 12/16. 

Inside the Annex, the construction crew will be working on the roof framing, and preparing to strip off the old roof before getting the new roof plywood down.

Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios remains prohibited during this time, as is foot traffic through the construction zone.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).

 

Kowalsky Construction Update 12/5-12/9

The framing of the partitions of the Kowalsky Addition's first floor are finished and the second floor deck is underway; by the end of the week (Friday, 12/9), the second floor walls will be put up.

The Kowalsky Annex's interior walls are about 50% completed on the first floor, and the new ridge support is now in place in the roof. The interior framing will continue there through 12/9 as well.

In the meantime, the mason will be working on the firewall between the Kowalsky Addition and the main house. 

At this time, parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios is prohibited, as is foot traffic through the construction zone.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).