Kowalsky Construction Update: 3/20-3/31

In the Kowalsky House Annex, interior finishing work is underway: windows, hanging doors and trimming, and stairs. 

The Kowalsky House Addition has been sided and a few exterior details will be completed in the coming week. The second floor interior is sheetrocked and taping is in process; the first floor sheetrock is being hung and should be completed soon.

At this time, construction is occuring between 8am-5pm daily. Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios is prohibited, as is foot traffic through the construction zone. 

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).
 

Kowalsky Construction Update 3/3-3/10

The Kowalsky Addition's roof is underway (photo courtesy Nicole Czapinski)

The Kowalsky Addition's roof is underway (photo courtesy Nicole Czapinski)

Monday, 3/6, the construction crew will begin priming and painting the interior walls of the Kowalsky Annex. The exterior will also receive a coat of paint, and the historic windows will be reinstalled.

In the Kowalsky Addition, the plumbing rough-in, electrical, and sprinkler work will be completed, and the interior will be insulated. The exterior siding and trim will be finished, and weather-permitting, the roof will be completed.

Construction will occur between 8am-5pm daily. Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios is prohibited, as is foot traffic through the construction zone. 

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).

Kowalsky Construction Update: 2/20-2/24

IMG_0935.JPG

For the rest of this week, the crew will be finishing up the deck and porch floor framing on the addition and will start on the porch roof next. The electrical in the addition is 90% roughed in and secondary service will be pulled in next week. The siding and trim on the addition is about 60% complete.

The Annex drywall hanging is nearly complete and the taping will begin soon. Finally, the exterior of the Annex is about 85% sided with the trim being complete.

Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios remains prohibited during this time, as is foot traffic through the construction zone.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).

Kowalsky Construction Update: 1/23-1/27

On Monday, 1/23, both the Annex and the Addition will undergo an air leak test to ensure that buildings' envelopes are sealed tight.
 
Throughout the week, the siding will go on the Addition, and the re-construction of the Annex exterior will continue.  Electrical rough-in will continue in the Addition along with the plumbing and mechanical rough-ins.  The electrical, plumbing, and mechanical rough-ins are nearly complete in the Annex; the crew will finish its weather and sound insulation and schedule sheetrock in the very near future.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).