Kowalsky Construction Update 11/14-11/18

Watch this week's video update. 

Watch this week's video update. 

This week, the conduits for the new electrical services to the Kowalsky Addition were dug and placed, and the basement slab placement will be completed by the end of the day on Friday, 11/11.

Beginning Monday, 11/14, there will be two separate crews working on site—one in the Kowalsky Annex, while the other frames the first floor of the Kowalsky Addition—while the dirt crew places the new water services to Mason and Kowalsky houses.
 
Due to this waterline work, parking in the driveway of Bivens House is prohibited. Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios remains prohibited as well, as does foot traffic through the construction zone.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).