Kowalsky Construction Update 11/7-11/11

Watch the action unfold in this exciting video!

Watch the action unfold in this exciting video!

This week the Addition foundation was placed and will be damp-proofed by Monday, 11/7. The excavation crew will be back on Tuesday, 11/8, to do footing drains, partial backfilling, and interior slab preparation.

Weather permitting, the team will place the basement slab either Thursday or Friday (11/10-11/11). The Annex carpentry crew will be back onsite full-time beginning next Wednesday, 11/9, and will begin framing the Addition the week of 11/14.  

Parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios remains prohibited, as does foot traffic through the construction zone.

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).