Kowalsky Construction Update: 5/1-5/12

(Photo courtesy Kieran Riley Abbott)

(Photo courtesy Kieran Riley Abbott)

Construction on the Kowalsky House Addition and historically preserved 1834 Annex is rapidly nearing completion!

The remaining site work includes: the topcoat on the driveway at Kowalsky and at Mason, seeding and mulching of the surrounding lawns, and the completion of the exterior decking and porch skirting.

The Annex is getting its final coat of interior paint, and the exterior painting should be finished up early the week of May 1st. The wiring in the Addition should be completed by May 5th, and the plumbing/heating is expected to wrap up by the 12th. The flooring work in both buildings is also expected be completed at that point. 

At this time, parking behind Kowalsky House and in the driveway between Kowalsky & Wolf Kahn Studios is prohibited, as is foot traffic through the construction zone. 

If you have any questions about Kowalsky House construction, please contact the VSC Main Office (802-635-2727) during business hours (weekdays 8:30am-5pm).