The Kowalsky House Project
Timeline
August-September 2016
Kowalsky Barn Deconstruction
October-November 2016
Groundbreaking and start of Construction- site work, site utilities, excavation, foundations and slabs, relocate Annex, demolition at West wall of Kowalsky House
December 2016-January 2017
Construction Continues- structural framing, exterior doors and windows, weathertight envelope, winterize
February-March 2017
Construction Continues- Interior framing and sheetrock, mechanical systems and equipment, interior walls and doors
April-May 2017
Construction Continues- interior and exterior finishes, millwork, plumbing fixtures, lighting, landscaping
May 15, 2017
Ribbon Cutting Ceremony
June 2017
Construction close-out, building commissioning & systems tuning, Punch List execution